The measuring tube is the same across most of our range. What differs is how the reading leaves the pit — and that decision outlives the meter, because the head-end system will still be running when the meters are replaced.
Four of them move the reading over the air; two keep it on a cable. The distinction that matters at procurement is not the radio technology — it is who owns and funds the network after commissioning.
Short answer Six uplinks are covered here: four wireless (LoRaWAN, NB-IoT, 4G Cat.1, Wi-SUN) and two wired (RS-485 / Modbus, M-Bus). The wireless half also has its own category page: wireless water meter.
| Uplinks covered | 6 — 4 wireless, 2 wired |
|---|---|
| Wireless | LoRaWAN, NB-IoT, 4G Cat.1, Wi-SUN |
| Wired | RS-485 / Modbus, M-Bus |
| Deciding question | Who owns and funds the network after commissioning |
| Uplink | What carries the data | Who runs the network | Fits when |
|---|---|---|---|
| LoRaWAN | A gateway you or the utility own; the meters join it | You, or the utility | Many meters in a small area, and someone to run the gateway |
| NB-IoT | The mobile operator's network, one subscription per meter | The operator | No gateway, meters spread across a city |
| 4G Cat.1 | The mobile network, with a larger data allowance | The operator | More than one reading a day, or over-the-air updates |
| Wi-SUN | A mesh between meters and a collector | You, or the utility | Dense clusters that should heal around a failed node |
| RS485 / Modbus | A cable to a local controller | The site owner | Plant rooms, skids, an existing BMS |
| M-Bus | A two-wire bus that also powers the meter | The site owner | Building metering with an M-Bus master already installed |
Unit price is the last thing to compare. These three settle the architecture, and the architecture is what the utility lives with for a decade.
Short answer Three questions settle the architecture before unit price is compared: who owns the gateway, who pays the SIM in year eight, and how many reads a day the fleet actually needs.
| Questions that settle the design | 3 |
|---|---|
| Normal read rate for revenue metering | 1 per day |
| Cost basis to compare | Total over the fleet’s life, not the first invoice |
4G Cat.1 belongs in the same conversation when you need more than meter readings on the link — firmware updates, valve commands or diagnostics pulled on demand.
Every upload costs radio time, and radio time is what drains the cell. The ten-year figure on our datasheets is tied to a daily upload schedule — change the schedule and you have changed the number.
Short answer The ten-year battery figure is quoted at one upload a day; change the read interval and the number changes with it.
| Battery life on the datasheet | 10 years |
|---|---|
| Interval that figure assumes | 1 upload per day |
| What shortens it | More reads a day, retries at the edge of coverage, valve operations |
| Valve-control models | The motor dominates the budget, not the radio |
RS-485 / Modbus and M-Bus are not legacy options. In a plant room, a basement with a controller, or a retrofit where the cable already exists, they remove the battery, the radio and the subscription in one decision.
Short answer Two wired options still win in plant rooms and retrofits — RS-485 / Modbus and M-Bus — because they remove the battery, the radio and the subscription in one decision.
| Wired protocols covered | 2 — RS-485 / Modbus, M-Bus |
|---|---|
| Power on M-Bus | Supplied by the bus — no cell to replace |
| Best fit | Plant rooms, skids, retrofits where the cable already exists |
Most integration delays are documents, not hardware. We issue these with the quotation so the head-end team can start before the meters ship.
Short answer Five documents decide whether the first reading lands on time: register map, pulse weight, join method and keys, APN and addressing, time and tariff handling.
| Documents issued with the quotation | 5 |
|---|---|
| Usual cause of integration delay | Documents, not hardware |
| When they are issued | With the quotation, before the meters ship |
Taken from the current specification table. The module is an order option on most families — confirm the combination you need when the model code is fixed.
Short answer Eight meter families are covered here, and on most of them the uplink module is an order option — the combination is fixed together with the model code.
| Families listed | 8 |
|---|---|
| LoRaWAN only | DN50 flanged |
| NB-IoT with Modbus | DN80 in-line |
| Widest uplink choice | DN15 LoRaWAN and XY-15 / XY-20 valve control — 4 wireless plus RS-485 / M-Bus |
| Family | Uplink options |
|---|---|
| DN15 LoRaWAN ultrasonic | LoRaWAN / NB-IoT / 4G Cat.1 / Wi-SUN, plus RS-485 / M-Bus |
| XY-15 / XY-20 valve control | LoRaWAN / NB-IoT / 4G Cat.1 / Wi-SUN, plus RS-485 / M-Bus |
| LXSY-15 / 20 / 25 non-magnetic | 4G Cat.1 / NB-IoT / LoRaWAN / Wi-SUN |
| LXCY-32~50 remote | LoRaWAN / NB-IoT |
| DN50 flanged | LoRaWAN |
| DN65 two-channel | LoRaWAN / NB-IoT / 4G / RS485 |
| DN80 in-line | NB-IoT with Modbus |
| LXCY-50~300 bulk | 4G / LoRaWAN / RS485 |
Details per protocol, including the models that carry a module as standard: LoRaWAN water meter and NB-IoT water meter.
Short answer Four questions cover most pre-order objections: gateway ownership, SIM cost across ten years, whether the module changes accuracy, and mixing uplinks in one fleet.
| Questions answered | 4 |
|---|---|
| Effect of the module on accuracy | None — metrology is set by the tube and the electronics, not the radio |
| Mixing uplinks in one fleet | Yes, per meter; the head-end has to speak both protocols |
We will come back with one recommended model, the wiring diagram and a quotation — not a 40-page catalogue.