Documents and approvals

What should come in the box: the paperwork behind a water meter

Six documents get called “the certificate” in tenders, and they prove six different things. This page sets out what each one actually establishes against ISO 4064 and OIML R49, what it does not, and how to check a document that lands on your desk.

First

Six documents, six different claims


The most common procurement mistake is treating these as interchangeable. A laboratory report and a certificate are produced by different bodies under different rules, and a tender that asks for one is not answered by the other.

DocumentIssued byWhat it establishesWhat it does not
ISO 4064 test reportA testing laboratory, accredited or notThat a sample was measured against the ISO 4064 procedure, and what the numbers wereThat a certification scheme accepted the design, or that every unit shipped matches the sample
OIML R49 report or certificateA laboratory, or an issuing authority acting under the OIML certification schemeThe same metrological evidence, expressed in the international recommendation that many national approval routes are written aroundAnything about production consistency unless a separate production module or audit is named
CNAS / ISO 17025 accreditationCNAS, for the laboratoryThat the lab is competent for the stated test scopeThat the product passed. Accreditation is held by the laboratory, never by the meter
CE declaration of conformityThe manufacturer, on its own responsibilityWhich directives the manufacturer declares the product meetsIndependent verification of anything. It is a self-declaration and only as good as the file behind it
WRAS, NSF/ANSI 61 and similarA hygiene or materials approval bodyThat the materials in contact with drinking water are accepted in that marketAccuracy, radio performance or billing approval
ISO 9001 certificateA certification body, for the factoryThat the quality management system is auditedNothing about the accuracy of any individual meter

This page explains how to read documents. It is not a statement of which approvals any particular model holds — ask for the file for the exact model and size you are ordering, and check the scope on it.

The two metrological standards

ISO 4064 and OIML R49 in one paragraph each


Everything a buyer actually argues about at acceptance sits in these two documents: the accuracy class, Q3, and the Q3/Q1 ratio.

Reading a tender

When the specification lists four standards at once


Tender documents often copy a list from an earlier project without pruning it. The list usually mixes three different things, and only one of them is what acceptance testing will check.

A supplier who answers all three with one PDF has usually handed you the management system certificate, because it is the easiest to obtain and the least informative. Ask specifically for the metrological evidence at the size you are buying.

Verification

Four checks that take ten minutes


None of these require the supplier's cooperation beyond sending the document itself. All four are worth doing before a bulk order, not after.

Red flags

Six mismatches that come up again and again


Each of these has appeared in a real tender pack. None of them means the supplier is dishonest — most mean the document was assembled by someone who had not read the annex either.

What you seeWhat to do
Report front page says DN15–DN50, annex lists only DN15–DN25Evidence is granted per size family. Ask for the annex page and read the size list, not the headline
“CE certificate” with no directive namedCE is not a certificate. Ask for the declaration of conformity and read which directives are cited
ISO 9001 presented as a product approvalISO 9001 is a quality management system certificate for the factory. It says nothing about meter accuracy
Report issued by a lab whose accreditation scope excludes flow testingCheck the accreditation schedule. A lab can be accredited for electrical safety and still issue an out-of-scope flow report
A standard number quoted that does not apply to water metersISO 4064 and OIML R49 are the water-meter documents. A report quoting an adjacent standard is evidence of something else
Test report dated after the shipping dateCommon in fast tenders. It means the units shipped before the evidence existed
From us

What we send with a quotation


Documentation is agreed per order, because the set differs by market and by whether the meter is for billing or for internal sub-metering.

For a tender, send the clause you have to satisfy and the size you need. We answer with the specific document for that model rather than a general pack. Request the set for your size — the model datasheets download without a form. See also the certifications page and how to fix the size.

Questions buyers ask about the paperwork

No. A test report records what was measured, on which sample, with which reference equipment, on a given date. A certificate states that a body has assessed conformity and carries a scope and a validity period. A tender that asks for a certificate is not answered by a report, and buyers who accept one for the other usually find out at acceptance testing or at the first dispute.

Usually one, not both. The two cover the same ground: metrological requirements, test methods and the Q3/Q1 relationship for cold potable and hot water meters. What a tender normally wants is evidence against one of them plus a declaration that the instrument meets the metrological requirements. Confirm with the buyer which document they will actually check, because a certificate against the wrong one is a week lost at acceptance.

It tells you the laboratory that produced the numbers was accredited to ISO/IEC 17025 for that kind of test, so the method and the reference equipment are audited. It says nothing about whether the product passed a certification scheme. Accreditation belongs to the laboratory, never to the meter.

Only if the document's annex lists DN50. Test evidence and certificates are granted for a stated size family and metrological class; a size outside the annex is not covered even when the housing looks identical. Read the annex, not the front page.

Only where the report says so and the temperature class supports it. The standard covers both cold potable water and hot water, but the evidence is per test condition, and the meter's stated temperature class is a hard limit rather than a margin. If the line runs hot, that class is the first line to check on the datasheet.

Not sure which meter fits

Send us the pipe size and the protocol you run

We will come back with one recommended model, the wiring diagram and a quotation — not a 40-page catalogue.

Choose your language

Interface translated. Technical documents stay in English.